Timeline

2021

u

Enabling works commence

Spring 

u

Infrastructure works begin with West Ham Station bridge enabling works

April

Works on new road bridge commences

April

Apprenticeship programme commences

June

Community engagement on Phase 2 application

August

2022 – Phase 2 planning decision

u

Milner Road Bridge complete & works on new road bridge complete

July

2023

u

Community centre opens

August

u

West Ham ticket station bridge complete and new station entrance opens

September

2024

u

Phase 2 works commence

January

u

Completion of first retail/commercial units and employment floorspace available to let

June

First 200 affordable homes available

July

2025

u

Phase 1 complete

October

u

First 290 private for rent homes available

October

By the end of phase 1 we will have created:

2,500

Construction jobs

Community centre

4,500

sq m of retail and commerical space

30%

of site wide public realm

315

Operational jobs

N

1,000

pupil secondary homes

1,048

Homes